Payment schedule
In construction, a payment schedule (or schedule of payments) is a list of dates setting out when payments will be made by one party to another under the terms of the contract between them. It can also also be linked to the completion or fulfilment of certain pre-agreed activities or stages, at which point payments must be made.
The Housing Grants, Construction and Regeneration Act 1996 was introduced with the purpose of ensuring that payments are made promptly throughout the supply chain and that disputes are resolved swiftly. Among the provisions included in the act was the right to be paid in interim, periodic or stage payments. Amendments made in 2011, established that dates for payments must be set out in the construction contract.
By including a payment schedule in the contract, setting out who needs to do what and by when, the likelihood of parties getting dates wrong (e.g. employer failing to serve a payment notice on time, or a contractor failing to serve an application for payment on the right date), can be reduced, and so disputes are less likely.
A payment schedule will usually include the following details:
- The starting date for the contract.
- The amount to be paid as an initial payment.
- The interval of other payments after the initial payment.
- The timeframe within which the project will be completed.
- The estimated total construction contract amount.
NB: In the case of Grove Developments Ltd v Balfour Beatty Regional Construction Ltd [2016] it was found that because the parties to the contract had not agreed to extend the payment schedule in the event that the works took longer to complete than expected, Balfour Beatty was not entitled to further interim payments and that the Scheme for Construction Contracts did not apply as there had been an adequate mechanism for payment.
As a result of this, contracts should set out how payments will be made if the works continue beyond the timeframe initially anticipated.
[edit] Related articles on Designing Buildings
Featured articles and news
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.